We near the end of October and the third floor office space and roof are the center of attention. The LVL (composite wooden) beams for the front section arrived late and Plan-It has started to frame in the third floor at the front. The wood trusses for the green room at the back are next to arrive. Closing in and being roof-tight should be achieved by the second week in November.